- Client PL Hotel Limited
- Status Pre-Construction
- Size 5,100 sq ft; 14 bedrooms
- Cost £2.5m
- Services Project Management
Synopsis
M3 managed the planning application process, design and construction for the extension and part refurbishment of the Marriott Hotel on Park Lane. Restricted access and a limited construction period led to the choice to construct the rooms as modules off site. We worked with the team through design and planning and are now procuring the construction phase to achieve delivery in 6 months.
Key Points
- Delivering 14 new hotel rooms to an existing hotel
- Extending 10 existing hotel rooms
- Minimising disruption to the hotel
- Utilising off site construction techniques
View all Projects: List View | Thumbnail View