Nine Elms Park

Wandsworth, SW8
Royal Mail Group
Phase 1 remediation completed 2016; Phase 1 infrastructure works completed 2018; Delivery ongoing
2.5m sq ft
£600m
Mixed use, residential, education, retail, public space and community

Allies and Morrison, Masterplan architect

Camlins, Landscape architect

Gleeds, Cost consultant

Steer Davies Gleeve, Transport consultant

Aecom, Building services engineer


At the heart of the Nine Elms regeneration area, Nine Elms Park is a 2.5m sq ft residential-led development centred on the Linear Park extending from Vauxhall Bridge to Battersea Power Station.

M3 has led the development of this project from early stage feasibility studies. Actively involved in shaping and delivering the strategic vision, M3 procured and led a consultant team through a complex design and planning process involving extensive local and regional consultations. Since securing consent, M3 has continued to coordinate works with neighbouring developments; resolve property issues; enable the site for development through remediation and infrastructure works; and lead the delivery and disposal strategy.


Related projects
Royal Mail Property Strategy

Project highlights


  • Establishing a strategy for redevelopment of the site

  • Leading design proposals which responded to emerging planning policy whilst maximising site value

  • Assisting in the resolution of complex property and title issues

  • Acting to protect Royal Mail’s operational interests

  • Developing relationships with adjoining developers

  • Securing robust planning consent

  • Effecting enabling works including demolition of redundant structures and remediation with delivery office in operation

  • Managing an extensive design team including 3 architectural practices to prepare reserved matters applications